# Construction Schedule of Values Template: Free Excel and PDF

> A free construction schedule of values template in Excel and PDF, with CSI lines, change orders, retainage, and payment due. How to fill in every column.

- URL: https://consight.ai/articles/schedule-of-values-template
- Published: 2026-11-02
- Topic: [Preconstruction & Estimating](https://consight.ai/articles/topics/preconstruction)
- Author: Stewart Toubia

A construction schedule of values (SOV) splits the contract sum into lines of work. Each line has a scheduled value, and the lines add up to the contract sum. Each month, the contractor bills against the same lines: work completed before, work completed this period, materials stored, total to date, percent complete, and balance to finish. The payer holds back retainage and pays the rest.

Download the free [schedule of values template in Excel](https://consight.ai/downloads/schedule-of-values.xlsx) or as a [printable PDF](https://consight.ai/downloads/schedule-of-values.pdf). A general contractor can use it to bill an owner, and a subcontractor can use it to bill a general contractor. The Excel file works out each line's total, percent complete, and balance. It then works out retainage and the payment due.

## What a schedule of values includes

A schedule of values includes one line per portion of the work, the scheduled value of each line, and the billing columns for each pay application. The table lists the columns in the template.

| Column                                | What it holds                                                               | Who fills it in                     |
| ------------------------------------- | --------------------------------------------------------------------------- | ----------------------------------- |
| Item and description of work          | One portion of the work, by spec section, trade, area, or floor             | You                                 |
| Scheduled value                       | That line's share of the contract sum                                       | You, once, before the first pay app |
| Work completed, previous applications | Work in place billed on earlier applications, without stored materials      | You, from the last application      |
| Work completed, this period           | Work put in place since the last application, including installed materials | You, each month                     |
| Materials stored, not yet installed   | Materials delivered for the work and not yet built in                       | You, each month                     |
| Total completed and stored to date    | Previous applications + this period + materials stored                      | Formula                             |
| Percent complete                      | Total to date ÷ scheduled value                                             | Formula                             |
| Balance to finish                     | Scheduled value − total to date                                             | Formula                             |
| Retainage                             | The share of each payment the payer holds back until the work is done       | Formula, from the rates you enter   |

Many US projects bill on AIA Document G703, the Continuation Sheet, or on a sheet with the same columns. AIA says G703 "is often used to record the submitted schedule of values" ([AIA Contract Documents](https://learn.aiacontracts.com/articles/6485259-what-is-a-schedule-of-values-and-why-is-it-required-on-construction-projects/)). The same article says A201-2017 Section 9.2 requires a schedule of values on a stipulated sum or guaranteed maximum price contract. The contractor submits it to the architect before its first application for payment.

AIA's [G703 instructions](https://help.aiacontracts.com/hc/en-us/articles/1500009308302-Instructions-G703-1992-Continuation-Sheet) say the retainage column is normally used only where retainage varies line by line. On most jobs one rate covers the whole application, so this template takes retainage on its Summary sheet. The template is our own sheet, not the AIA form. If your contract requires G702 and G703, buy them from AIA and copy your lines across.

## What the schedule of values template includes

The template has four sheets after its instructions. Shaded number cells hold the formulas.

| Sheet              | What it holds                                                                                  |
| ------------------ | ---------------------------------------------------------------------------------------------- |
| Project            | Job, owner, general contractor, subcontractor, contract number, application number, and period |
| Schedule of values | 34 sample lines under CSI divisions, six blank lines, and totals                               |
| Change orders      | Ten lines for approved change orders, with the same columns and totals                         |
| Summary            | Contract sum to date, a check that your lines add up, retainage at two rates, and payment due  |

The sample lines are a general contractor's schedule of values for a commercial building, from Division 01 general conditions to Division 33 site utilities. A subcontractor replaces them with its own trade's lines.

## How to fill in each column

Fill in the scheduled values once, before the first pay application. Then fill in three billing columns each month.

1. **Item and description of work.** Write one line per portion of the work. AIA's G703 instructions say the breakdown "may be by sections of the Work or by Subcontractors and should remain consistent throughout the Project."
2. **Scheduled value.** Give each line its share of the contract sum. AIA says the total "should equal the original Contract Sum." The Summary sheet shows the difference, which should read $0.
3. **Work completed, previous applications.** Enter the work billed on earlier applications. Leave stored materials out of this column. They stay in Materials stored until you install them.
4. **Work completed, this period.** Enter the value of the work put in place since the last application, including the materials you installed.
5. **Materials stored, not yet installed.** Enter the value of materials on hand that you bill for now. Work out this column again each period. AIA's instructions say stored materials leave this column only "as materials are incorporated into the Project."
6. **Total, percent complete, and balance.** The template adds the three billing columns, divides the total by the scheduled value, and subtracts the total from the scheduled value.
7. **Retainage.** On the Summary sheet, enter your contract's rate on completed work and its rate on stored materials.
8. **Payment due.** On the Summary sheet, enter the amount paid or certified on earlier applications. The template subtracts it from the total earned less retainage.

For the next application, save a copy of the file. On each line, add This period into Previous applications, then clear This period.

## A filled-in schedule of values example

The example below is a drywall and framing subcontractor's third pay application, with sample numbers. The subcontract sum is $640,000, and one approved change order adds $8,500. The subcontract holds back 10% retainage on completed work and on stored materials.

| Item  | Description of work                  | Scheduled value | Previous applications | This period  | Materials stored | Total to date | Complete  | Balance to finish |
| ----- | ------------------------------------ | --------------- | --------------------- | ------------ | ---------------- | ------------- | --------- | ----------------- |
| 1     | Mobilization, submittals, and layout | $12,000         | $12,000               | $0           | $0               | $12,000       | 100%      | $0                |
| 2     | Bonds and insurance                  | $9,600          | $9,600                | $0           | $0               | $9,600        | 100%      | $0                |
| 3     | Exterior metal stud framing          | $118,000        | $70,800               | $35,400      | $0               | $106,200      | 90%       | $11,800           |
| 4     | Exterior gypsum sheathing            | $46,000         | $13,800               | $23,000      | $4,600           | $41,400       | 90%       | $4,600            |
| 5     | Interior framing, Level 1            | $64,000         | $32,000               | $25,600      | $0               | $57,600       | 90%       | $6,400            |
| 6     | Interior framing, Level 2            | $61,000         | $0                    | $30,500      | $12,200          | $42,700       | 70%       | $18,300           |
| 7     | Hang gypsum board, all levels        | $142,000        | $0                    | $28,400      | $21,300          | $49,700       | 35%       | $92,300           |
| 8     | Tape and finish, all levels          | $126,400        | $0                    | $0           | $0               | $0            | 0%        | $126,400          |
| 9     | Shaft wall assemblies                | $38,000         | $0                    | $0           | $7,600           | $7,600        | 20%       | $30,400           |
| 10    | Closeout: punch list and cleanup     | $23,000         | $0                    | $0           | $0               | $0            | 0%        | $23,000           |
|       | **Original subcontract**             | **$640,000**    | **$138,200**          | **$142,900** | **$45,700**      | **$326,800**  | **51.1%** | **$313,200**      |
| CO 01 | Added in-wall backing, Level 2       | $8,500          | $0                    | $8,500       | $0               | $8,500        | 100%      | $0                |
|       | **Total with change orders**         | **$648,500**    | **$138,200**          | **$151,400** | **$45,700**      | **$335,300**  | **51.7%** | **$313,200**      |

The Summary sheet turns those totals into the payment due. The previous payment is the second application's $156,200 of work and stored materials, less 10% retainage.

| Summary line                                   | Amount   |
| ---------------------------------------------- | -------- |
| Original subcontract sum                       | $640,000 |
| Net change from approved change orders         | $8,500   |
| Contract sum to date                           | $648,500 |
| Total completed and stored to date             | $335,300 |
| Retainage on completed work (10% of $289,600)  | $28,960  |
| Retainage on stored materials (10% of $45,700) | $4,570   |
| Earned to date, less retainage                 | $301,770 |
| Paid or certified on previous applications     | $140,580 |
| Payment due this application                   | $161,190 |
| Balance to finish, including retainage         | $346,730 |

## What the example schedule of values tells you

The example bills $161,190 this period. Its total to date includes $45,700 of stored materials. Before you pay for stored materials, check the delivery tickets and walk the site. Line 7 alone carries $21,300 of board that nobody has hung yet.

Lines 1 and 2 billed in full on early applications. That is normal when their values match real costs, such as the bond premium on the surety's invoice. Line 10 keeps $23,000 back for the punch list and cleanup, so the subcontractor still has money to earn at the end.

## How to break the contract sum into lines

A general contractor usually breaks the contract sum out by CSI division and spec section. The [Section 01 29 73, Schedule of Values](https://tennessee.edu/wp-content/uploads/2025/04/DM-Appx2_01-29-73-Schedule-of-Values-2018-05.pdf) that the University of Tennessee publishes is a typical owner's rule. It asks the contractor to "categorize items by major trades or units of work corresponding to the divisions and sections of the specifications."

The same section asks for a line for each allowance and the total equal to the contract sum. It also asks for one line for each fully executed change order, by its number. AIA's G703 instructions say change orders usually go on their own sheet or at the end of the schedule. Read your project's own Section 01 29 73 first, because it may set a different breakdown.

A subcontractor breaks its own trade down by system, floor, or area. Some general contractors also ask for labor and material on separate lines. Kevin O'Beirne, writing for [CSI](https://www.csiresources.org/blogs/kevin-obeirne-pe-fcsi-ccs-ccca-cdt1/2022/12/13/progress-payments-schedules-of-values-part-2-const), says "greater detail in the schedule of values usually supports more efficient processing of progress payment requests." Smaller lines leave less to argue about each month.

## What front-loading is and how to spot it

Front-loading means putting more value on early lines than their work costs, and less on late lines. The contractor then bills ahead of the work and collects cash early. If the contractor walks off the job, the balance left on the late lines may not pay someone else to finish.

Look for front-loading in three places:

- **Early lines.** Compare mobilization, bonds, general conditions, and the first trades' lines with your own estimate.
- **Late lines.** Finishes, testing, and closeout lines that look too low are the other half of the same move.
- **Lines with no backup.** Ask for the bond and insurance invoices, and for the cost behind any line that looks out of scale.

O'Beirne's CSI article gives reviewers the same test. Checking that each line's value is reasonable for its work "helps reduce the potential for 'front-end loading.'" When a value looks obviously low or high, he says to ask for backup. A low line may mean the rest of its cost sits on another line.

## How a general contractor reviews a subcontractor's schedule of values

Review each subcontractor's schedule of values against its subcontract and the bid you leveled, before its first pay application. The leveled bid holds the best price data you have on that subcontractor's work.

1. **Check the total.** The lines should add up to the subcontract sum, including any alternates you accepted.
2. **Check the scope.** Every scope item in the subcontract should land on a line. Work the bidder excluded, and that you bought from another subcontractor, should not appear.
3. **Check the lines against the bid.** Compare each line with the breakout prices the bidder gave on your [scope sheet](https://consight.ai/articles/scope-sheet-template). A shaft wall line far from the bidder's own shaft wall price needs a call.
4. **Check the early and late lines.** Compare them with your estimate, as in the front-loading test above.
5. **Split lines with stored materials.** Ask for long-lead items on their own lines, so stored materials bill against a clear value.
6. **Settle the schedule before the first application.** The Tennessee section tells the contractor to revise and resubmit an SOV the designer or owner objects to, before it submits a pay application.

Your [bid leveling template](https://consight.ai/articles/bid-leveling-template) or bid tab shows each line's status and the plugs you added. For the full method, read [how to compare subcontractor bids](https://consight.ai/articles/how-to-compare-subcontractor-bids).

## Retainage and stored materials follow the contract

Your contract sets the retainage rates and the rules for stored materials. AIA's guide to the [G702 payment application](https://learn.aiacontracts.com/articles/how-to-complete-the-g702-payment-application) says "retainage requirements come from the contract documents and may also be affected by applicable law."

Federal fixed-price construction contracts follow [FAR 52.232-5](https://www.acquisition.gov/far/52.232-5). The contracting officer pays in full when progress is satisfactory. When progress is not satisfactory, the officer may hold back up to 10% of the payment. The officer counts materials stored off the site only when the contract allows it. The contractor must also show title and that the materials will be used on the contract.

The template takes separate rates for completed work and stored materials, because some contracts set them apart. Enter the same rate twice when your contract has one.

## How Consight fits

In Consight, each bid package has a scope sheet. Your scope items run down the left, and bidders run across the top, as the help center's [scope sheet guide](https://consight.ai/reference/scope-sheets#what-a-scope-sheet-does) shows. Each cell shows what that bidder said about that scope item.

Download saves a package's scope sheet as an Excel file. Keep the awarded bidder's column with the subcontract. When that subcontractor's schedule of values arrives, you can check its lines against the scope the bid covered.