Common Exclusions in Subcontractor Bids, by Trade

Photo of Chris ToubiaChris ToubiaPreconstruction insights

Subcontractors most often exclude permits (63%), cleanup (61%), testing (60%), bonds (56%), and patching (56%). Without the largest organization, those shares are 63%, 59%, 62%, 56%, and 57%. They come from 2,426 bids that state an exclusion, across 26 organizations, as our AI read them.

By trade, Electrical bids exclude at least one of your scope line items most often, at 68% (68% without the largest organization). General Requirements bids do so least, at 42% (39% without it). On bid day, ask each bidder who carries each excluded item, then assign it or plug it, as the table in "What do you do about each common exclusion?" shows.

All figures come from our bid benchmark snapshot of November 9. Each table gives the value with and without the largest organization in the sample, because one organization supplies a large share of most samples. The method is at the end, under How we measured.

Which exclusions do subcontractors list most often?

Permits, cleanup, testing, bonds, patching, and concrete pads each appear in more than half of all exclusion lists. Every row below is the share of bid exclusion lists that name the category. The sample is 2,426 leveled bids that state at least one exclusion, from 737 packages, 70 projects, and 26 organizations. The largest organization holds 26% of those bids. The figures are AI-detected.

What the exclusion list names Share of exclusion lists Without the largest organization
Permits or fees 63% 63%
Cleanup, dumpsters, or disposal 61% 59%
Testing or inspection 60% 62%
Bonds 56% 56%
Patching or painting 56% 57%
Concrete or equipment pads 52% 52%
Engineering or design 47% 51%
Cutting, coring, or sleeves 46% 46%
Temporary power, water, or facilities 46% 45%
Demolition 41% 44%
Overtime or after-hours work 36% 39%
Hazardous materials 35% 39%
Excavation, rock, or backfill 32% 33%
Hoisting, cranes, or lifts 27% 23%
Fire stopping or fire rating 26% 24%
Sales or use tax 22% 24%
Winter conditions or weather protection 9% 8%
Utility company charges or connections 7% 7%

One bid's list can name several categories, so the rows add up to more than the whole. The top rows share one trait. Each is work that more than one party could carry: the general contractor, the owner, or another trade. No single subcontractor owns cleanup, testing, or permits unless your bid documents assign it.

What do you do about each common exclusion?

For each common exclusion, ask the bidder one question, then assign the work to the party your documents name or plug it yourself. Check your contract and drawings first, because the answer changes by project.

Exclusion Ask the bidder Assign or plug
Permits or fees Does your price include your trade permits and inspection fees? Assign the building permit to the general contractor or owner. Plug only the permits your contract puts on this trade.
Cleanup, dumpsters, or disposal Do you haul your own debris, or do you use the general contractor's dumpster? Assign dumpsters and final cleaning to general conditions. Plug a haul-off allowance when the sub must haul.
Testing or inspection Which tests does your price cover, such as startup, weld, or pressure tests? Assign third-party special inspections to the owner's testing agency when your contract does. Plug the sub's own tests.
Bonds What does the bond cost, and can you hold the price without it? Plug the bond premium, from the bidder's quote, if your contract or policy requires bonded subs.
Patching or painting Who patches and paints after your cuts and penetrations? Assign it to the finishes trade, or carry one patching allowance. Name the owner in writing.
Concrete or equipment pads Who pours the pads for your equipment? Assign the pads to the concrete trade, and add the equipment sizes to its scope. Plug if no one carries them.
Cutting, coring, or sleeves Who cores the slabs and sets the sleeves? Assign each task to one trade in writing. Plug the coring cost for the bid that excludes it.
Engineering or design Who stamps the shop drawings or design-build drawings? Plug the engineer's fee, or move the design to the design team if your contract allows.
Temporary power, water, or facilities What temporary services does your price assume? Assign them to general conditions. Plug only when the general contractor will not supply them.
Demolition Where does your demolition stop, and who hauls the debris? Assign the demolition limits on the drawings. Plug the demolition no one else carries.
Overtime or after-hours work Does your price assume normal working hours? Plug the premium only when the schedule needs extra shifts.
Hazardous materials What do you do when you find it, and who tests for it? Assign testing and abatement to the owner or an abatement trade. Carry abatement as its own line.
Excavation, rock, or backfill Does your price assume no rock and no shoring? Ask for unit prices for rock and shoring. Plug an allowance until the geotechnical report settles it.
Hoisting, cranes, or lifts Do you carry your own crane or lift? Price the crane time, or add it to general conditions when several trades use it.
Fire stopping or fire rating Do you seal your own penetrations? Name who seals each trade's penetrations, or carry one firestopping package.
Sales or use tax Does your price include sales or use tax? Plug the tax when your project is taxable and the bid leaves it out.
Winter conditions or weather protection Does your price assume pours or work in cold weather? Plug heat and protection when you work in winter. Ask for the unit cost per day.
Utility company charges or connections Who pays the utility's fees and connection work? Assign them to the owner or general contractor when your documents say so. Plug a placeholder until the utility quotes.

Which trades exclude the most scope?

Electrical bids exclude at least one of your scope line items most often, at 68%. Metals and Concrete follow at 67% and 66%. Without the largest organization, Metals ranks first at 71%.

The share counts leveled bids that leave out one or more line items on the package's scope sheet. A line item counts as excluded when the bid's coverage marks it excluded. A line item the bid gives no sign about counts as unclear, not excluded. All of these figures are AI-detected.

Trade (CSI division) Bids excluding a line item Without the largest organization Sample
Electrical (26) 68% 68% 350 bids, 103 packages, 29 orgs
Metals (05) 67% 71% 268 bids, 85 packages, 25 orgs
Concrete (03) 66% 66% 383 bids, 96 packages, 33 orgs
Existing Conditions (02) 66% 67% 209 bids, 71 packages, 18 orgs
Earthwork (31) 63% 61% 220 bids, 65 packages, 21 orgs
Masonry (04) 60% 63% 115 bids, 43 packages, 20 orgs
Thermal and Moisture Protection (07) 58% 56% 480 bids, 162 packages, 28 orgs
HVAC (23) 56% 50% 246 bids, 76 packages, 25 orgs
Fire Suppression (21) 55% 51% 144 bids, 53 packages, 15 orgs
Plumbing (22) 55% 57% 199 bids, 67 packages, 25 orgs
Finishes (09) 54% 51% 913 bids, 275 packages, 31 orgs
Wood and Millwork (06) 53% 48% 277 bids, 97 packages, 22 orgs
Openings (08) 51% 51% 550 bids, 199 packages, 31 orgs
Exterior Improvements (32) 50% 48% 331 bids, 107 packages, 23 orgs
Specialties (10) 49% 48% 286 bids, 120 packages, 16 orgs
Electronic Safety and Security (28) 49% Withheld 95 bids, 41 packages, 9 orgs
Furnishings (12) 45% Withheld 201 bids, 67 packages, 11 orgs
General Requirements (01) 42% 39% 187 bids, 91 packages, 18 orgs

"Withheld" means too few packages or organizations remain once the largest organization is set aside, so we print no number. Equipment, Conveying Equipment, Communications, and Utilities had too few packages to publish at all.

How often does the low bid exclude scope?

The low bid excludes at least one line item in 68% of leveled packages (67% without the largest organization). That figure covers 336 packages from 66 projects and 24 organizations, each with two or more comparable prices, all leveled. It is AI-detected. In most packages, then, you must plug the low bid's gaps before you know whether it is still low.

In 41% of those packages, the low bid leaves more line items excluded or unclear than the median rival does (42% without the largest organization). The sample and basis are the same.

Unclear scope adds to the risk. 43% of leveled bids leave at least one line item unclear, meaning the bid neither includes nor excludes it (50% without the largest organization). That sample is 6,013 bids from 2,025 packages, 199 projects, and 67 organizations, and it is AI-detected.

How many bids exclude a scope line item?

55% of leveled bids exclude at least one scope line item (55% without the largest organization). 40% of leveled bids had exclusions captured as Exclusions rows in Consight (45% without the largest organization). Both figures are AI-detected, over 6,013 bids from 2,025 packages, 199 projects, and 67 organizations.

The exclusion lists in the first table come from 2,426 bids at 26 organizations. So the 40% measures which bids hold Exclusions rows, not what every bid document says, and the two figures do not compare directly.

The share holds when an estimator checks the calls. Counting only estimator-reviewed calls, 56% of bids exclude a line item (62% without the largest organization). That sample is 2,684 bids from 988 packages, 153 projects, and 60 organizations. Read the exclusion list first, then check every scope line the list does not mention.

What should you check in each trade's exclusions?

This section draws on the spec sections and the sources linked below, not on counts from bids. Check each trade for the categories that sit on its edges, and settle in your bid documents who carries each one. Trades follow CSI MasterFormat divisions.

Trade Exclusions to check
General Requirements Cleanup, temporary power and water, testing
Existing Conditions Hazardous materials, demolition limits
Concrete Equipment pads, winter conditions
Metals Engineering or design, hoisting
Thermal and Moisture Protection Fire stopping, patching
Finishes Patching and painting, cleanup
Fire Suppression Engineering or design, permits
Plumbing and HVAC Cutting and coring, equipment pads, and test and balance
Electrical Temporary power, utility company charges, fire alarm
Earthwork Rock, backfill, trench protection

What do the codes and standards say about these exclusions?

Some exclusions point to work a code or standard requires, so someone must carry it. Use these to decide whether to plug a bid or assign the work elsewhere.

  • Hazardous materials. Federal rules require the owner or operator to "thoroughly inspect the affected facility" before demolition or renovation begins (40 CFR 61.145). Get that survey before you level demolition bids, and carry abatement as its own line until it is clear.
  • Bonds. On federal work, the Miller Act, as FAR 28.102-1 restates it, "requires performance and payment bonds for any construction contract exceeding $150,000." If your contract or your own policy requires bonded subs, plug the bond cost for every bid that excludes it.
  • Excavation. OSHA says the estimated location of underground utilities "shall be determined prior to opening an excavation" (29 CFR 1926.651). It requires a protective system against cave-ins unless the excavation sits in stable rock or runs under 5 feet deep with no sign of cave-in (29 CFR 1926.652). An earthwork bid that excludes rock or shoring needs a plug or a unit price.
  • Hoisting. OSHA's crane rules cover equipment "that can hoist, lower and horizontally move a suspended load" (29 CFR 1926.1400). When a steel or mechanical bid excludes cranes, price the crane time or add it to your general conditions.
  • Fire stopping. Name in each trade's scope who seals its own penetrations, or carry one firestopping package.
  • Test and balance. The National Environmental Balancing Bureau offers certification for testing, adjusting, and balancing (NEBB). Check that the HVAC bid or a separate test and balance bid carries it.
  • Sprinkler design. NFPA 13 is the Standard for the Installation of Sprinkler Systems (NFPA). When a fire suppression bid excludes engineering, find out who will produce the design and permit drawings.

How do you plug a common exclusion?

You plug an exclusion by adding your own estimate of the missing work to that bidder's leveled price. That way every bidder is compared on the same scope.

  1. Read the bid's exclusion list against your scope sheet, one line at a time.
  2. Check every scope line the list does not mention. Silence is not coverage.
  3. Decide who should carry each excluded item: this trade, another trade, your general conditions, or the owner.
  4. Add a labeled plug for each item this trade should carry, priced from your estimate or another bidder's price.
  5. Ask the bidder to confirm or price the gap before award.

Consight reads each bid and answers your scope sheet's rows from it. Each row shows Included, Not Included, or Needs Review for each bidder. Consight also adds the exclusions a bidder states to the Exclusions section.

You then add a plug for missing or unclear scope to the bidder's leveled price. For the full method, read how to find scope gaps in subcontractor bids. For mechanical and electrical packages, see how to level mechanical and electrical bids.

How we measured

Every figure comes from our bid benchmark snapshot dated November 9, computed read-only from production bid data. The snapshot leaves out our own organizations, deleted and archived records, and test, demo, sample, and training projects.

A leveled bid is an active bid with at least one coverage call on a bidder-facing scope line item. Each call marks the line item excluded, included, or unclear. AI-detected figures count every call, whether or not an estimator has reviewed it.

Estimators have confirmed or changed 36% of all coverage calls (30% without the largest organization), a recorded figure over the full sample of 6,013 bids. Of the calls they reviewed, they changed 5% (4% without the largest organization), an estimator-reviewed figure over 2,684 bids. A change may fix the call itself or only its price or note.

A bid's stated exclusions are the Exclusions rows on its package's scope sheet that its coverage marks excluded. The AI captures each exclusion it reads from a bid document in such a row, and estimators, templates, and imports add others.

A category matches on the row's name, so a row worded in an unusual way can miss its category. Trades follow CSI MasterFormat divisions: a package takes the division most of its cost codes name, else the trade its name matches.

The snapshot suppresses any figure from fewer than 5 organizations or fewer than 30 packages. Each figure also has a value without the organization that contributes the most bids. That organization holds 25% or more of the sample in most figures above, so each table gives both values. The snapshot has no trend over time. It names no customer and publishes no single bid's amount.

Where Consight fits

Consight is the preconstruction workspace built around this kind of work—from understanding project documents and building scopes to collecting bids, leveling proposals, reviewing risk, and documenting the final award.

Put it into practice on your next project.

Talk to sales

Trust your bid on bid day. Get Consight.

Start now