Bid Leveling Template for Excel: Free Subcontractor Bid Tab

Photo of Stewart ToubiaStewart ToubiaPreconstruction insights

Download a free bid leveling template in Excel. It is one sheet for one trade package and up to four bidders, laid out the way estimators level bids at a general contractor. Your own estimate sits beside each bidder's numbers. Each adjustment is tagged as a sub-based plug, a GC allowance, or an internal contingency. The sheet then ranks the bidders by leveled price, not by the price on page one.

What should a bid tab include?

A bid tab should hold every number and answer you need to award on equal terms. Each part of the template answers one question you will face before award:

Part of the bid tab Why the bid tab needs it
Job name, trade, and drawings set Every bidder must price the same documents, so the drawing set sits at the top.
Selected bidder Type the winning bidder's name, and the sheet looks up their leveled price.
Estimated cost column Your own quantity, unit, unit rate, and total for each line, to check the bids against.
Leveled price and base bid The base bid is the price each bidder signed. The leveled price is the number you compare.
Scope of work by location One fixed list lets you measure every bid against your scope, not against each other.
Quantity, total, and ID for each bidder The ID tags each added amount: P for a plug based on another sub's price, A for a GC allowance, C for an internal contingency.
Tax, Textura fee, and bond cost Rates you set once. Mark Y or N for each bidder, and the sheet adds what their bid leaves out.
Alternates, inclusions, and exclusions Alternates stay out of the leveled total until the owner decides.
Bid leveling metrics Plug, allowance, and contingency totals for each bidder, each as a share of the base bid.
Low bid, delta, spread, and rank Shows whether the low bid is still lowest, and by how much.
Qualifications Documents, safety (EMR), insurance, bonding, schedule, labor, and how long the bid holds.

The joint AGC, ASA, and ASC Guidelines for a Successful Construction Project say each subcontractor's scope letter should state its proposed scope, alternates, unit prices, and the addenda it includes. The guidelines also say the scope should name spec divisions or sections and identify any omissions or additions. So give the bid tab a line for each of those, plus anything else your bid documents require, such as safety records or union labor.

How do you fill in the bid leveling template?

  1. Fill in the header. Enter the job name, replace [TRADE] with your trade package, and note the drawings set the bids are based on.
  2. Name the bidders. Type each bidder's name over [Bidder 1] to [Bidder 4].
  3. List your scope. Under Scope of work, write one line per item, grouped by location. Add your own quantity, unit, and unit rate in the Estimated cost columns.
  4. Enter each base bid. Copy the price from each bid form into that bidder's Base Bid row.
  5. Read every proposal line by line. Include the exclusions and qualifications on the last page. Note what each bidder covers in their Quantity column.
  6. Add an amount for each gap. When a bidder leaves out a line, enter your price for it in their Total column. Tag it in the ID column: P, A, or C.
  7. Set tax, fees, and bond. Enter the rates once, then mark Y or N for each bidder.
  8. Enter alternates, inclusions, and exclusions in their rows below the leveling total.
  9. Read the metrics. The sheet shows each bidder's plug, allowance, and contingency totals, their gap to the low bid, and their rank. Write your take on each bidder in the Analytical summary row.
  10. Call the bidders. Ask each bidder about every line they left out or left unclear. Get the answers in writing, then remove the amounts they settle.
  11. Pick the winner. Type their name in Selected bidder.

What does a filled-in bid tab look like?

The example below uses sample numbers for a drywall and framing package with three bidders. All three bidders included every line not shown. Every added amount is a plug (ID P).

Scope line Bidder 1 Bidder 2 Bidder 3
Base bid $1,184,000 $1,236,500 $1,249,000
Acknowledges every addendum issued Included Unclear, plug $6,000 Included
Bond cost included where the bid documents require a bond Excluded, plug $14,200 Included Included
Meets the project schedule Included Included Unclear, no plug
Hoisting, staging, and distribution of own materials Included Unclear, plug $7,500 Included
Delegated design and stamped calculations for exterior framing Excluded, plug $18,500 Included Included
Fire-rated head-of-wall joints at rated partitions Excluded, plug $21,800 Included Included
Shaft wall at elevator and mechanical shafts Excluded, plug $46,200 Included Included
In-wall blocking and backing for owner and trade items Included Excluded, plug $12,400 Included
Finish levels as specified (Level 4 typical, Level 5 where noted) Unclear, plug $9,600 Included Included
Plugs $110,300 $25,900 $0
Leveled price $1,294,300 $1,262,400 $1,249,000
Alternate 1 (not in the leveled price) $22,000 $19,800 $24,500

Ranked by leveled price:

Bidder Base bid Plugs Leveled price Rank Delta from low bid Spread from low bid
Bidder 1 $1,184,000 $110,300 $1,294,300 3 $45,300 3.6%
Bidder 2 $1,236,500 $25,900 $1,262,400 2 $13,400 1.1%
Bidder 3 $1,249,000 $0 $1,249,000 1 $0 0.0%

What does the example bid tab tell you?

The example bid tab shows the low base bid finishing last. Bidder 1 came in $52,500 under Bidder 2 on base bid. After $110,300 of plugs, Bidder 1 sits $45,300 above the low leveled price.

The open questions still matter. Bidder 3 leads, but its schedule answer is unclear, so you call Bidder 3 before you award. Bidder 2 may confirm the addendum. That removes the $6,000 plug and leaves Bidder 2 at $1,256,400, still $7,400 over Bidder 3.

How do you choose a plug amount?

A plug is your best price for the work a bidder left out. Use your own estimate, another bidder's price for the same line, or cost from a past job. For a conservative plug, take the higher of two bidders' prices for that line.

Plugs can go both ways. BuildingConnected's help center describes plugs in its bid leveling tool as positive or negative values that only your team sees. The template works the same way: a negative plug takes out work a bidder carried that belongs elsewhere. For more on spotting the gaps, read how to find scope gaps in subcontractor bids.

Why do alternates stay out of the leveled total?

Alternates stay out of the leveled total because the owner has not accepted them yet. If you add them in, the bidder with the most alternates looks expensive for scope that may never get built. The template keeps alternates in their own rows below the leveling total.

When the owner accepts an alternate, add its price to each bidder's comparison by hand. Then check whether the rank changes. In the example, Alternate 1 would add $24,500 to Bidder 3 and $19,800 to Bidder 2. Bidder 3 would still lead, but by $8,700 instead of $13,400.

Where does a spreadsheet bid tab stop working?

A spreadsheet bid tab works well for one package with a few bidders and one estimator. It gets harder when the bid tab grows. In an audit of 50 working spreadsheets published in an academic journal, Powell, Baker, and Lawson found errors that gave wrong results in 43 of them. The most common error overall was a number typed into a formula instead of taken from an input cell.

On bid day the same risks show up in familiar ways:

  • Retyping. You copy every price and exclusion from a PDF by hand, and one transposed digit moves a rank.
  • Overwritten formulas. Someone types a number over a total, and the leveled total stops updating.
  • Revised bids. A bidder sends a new number at 1:45 p.m., and the old status marks stay in place.
  • Many packages. Twenty trade packages mean twenty files, each with its own copy of the formulas.

Software can take over the reading and retyping. Consight reads each proposal PDF and fills the bidder columns of your scope sheet against your scope items. It sorts inclusions, exclusions, alternates, and qualifications into their own tabs and sets aside matches it is unsure of for your review.

You still enter the plugs and make the award call, and Download exports the scope sheet to Excel. For the full method with or without software, see how to compare subcontractor bids.

Where Consight fits

Consight is the preconstruction workspace built around this kind of work—from understanding project documents and building scopes to collecting bids, leveling proposals, reviewing risk, and documenting the final award.

Put it into practice on your next project.

Talk to sales

More articles

Trust your bid on bid day. Get Consight.

Start now