A scope sheet is the list of one trade's scope line items that you send with the bid package. Each subcontractor marks every line Included, Excluded, or Unclear, prices the lines you ask for, and returns the sheet with the bid. So the scope sheet is also the bid form, and every bid you get back covers the same scope.
Download the free scope sheet template in Excel or as a printable PDF. It holds one bid package for one bidder. The sample lines are a Division 09 drywall and framing package, grouped by spec section. Replace them with your own trade's lines before you send it.
What the scope sheet template includes
The template has three sheets after its instructions. You fill in the top of the first sheet and the scope lines. The bidder fills in the rest.
| Part of the scope sheet | What it holds | Who fills it in |
|---|---|---|
| Bid package header | Project, trade, bid package, drawings and spec sections issued, addenda issued, bid due time | You |
| Bidder header | Company, contact, addenda acknowledged, days the bid holds, tax, bond, insurance, signature | Bidder |
| Base bid | The lump sum the bidder signs for, at the top of the Scope sheet | Bidder |
| Scope lines by spec section | One priceable item per line, under its MasterFormat section number | You |
| Status column | Included, Excluded, or Unclear for every line | Bidder |
| Price column | A price on each line you mark "(break out price)", plus each allowance | Bidder |
| Lines you add | Eight blank rows for work in the bid that your list missed | Bidder |
| Totals | Prices entered on Included lines, the rest of the base bid, and a count of each status | Formulas |
| Alternates and unit prices | Priced on their own rows, outside the base bid | Bidder |
| Exclusions sheet | Every exclusion and qualification, with the line or spec section it affects | Bidder |
The totals add only lines marked Included. A price typed on an Excluded or Unclear line stays out of the sum, so a stray number cannot inflate the breakout.
How a scope sheet differs from the subcontract scope of work
A scope sheet is a bid-time form: a list of lines each bidder marks and prices so you can compare bids. The subcontract scope of work is the contract exhibit you write after award. It states what the chosen subcontractor must furnish and install, in contract language.
The two documents share their lines. You build the scope of work from the scope sheet, plus the answers the winning bidder gave on its Unclear lines and exclusions. For the contract version, see how to write a subcontractor scope of work.
Trade groups expect this kind of written scope from every bidder. The AGC, ASA, and ASC Guidelines for a Successful Construction Project ask each subcontractor to send a written scope at least 24 hours before the bid hour. That scope sets out the proposed work, alternates, unit prices, and addenda. It should reference spec divisions or sections and name any omissions or additions.
The same guidelines ask the general contractor to furnish any special bid proposal forms the bid requires. A scope sheet is that form, with the lines already written.
How to build a scope sheet from the drawings and specs
Build the scope sheet from the project manual first, then check it against the drawings. Use the section numbers in your project's specs. Spec books follow different MasterFormat editions, and CSI's 2026 edition reorganized 617 listings (CSI).
- List the spec sections in the package. CSI says MasterFormat organizes specifications "into work results that contractors can price, procure, and build." A drywall package usually starts with 09 21 16 Gypsum Board Assemblies, 09 22 16 Non-Structural Metal Framing, and 09 29 00 Gypsum Board, as numbered in MasterFormat 2016.
- Add the gray-area sections from other divisions. Drywall bids often touch 05 40 00 Cold-Formed Metal Framing, 06 16 43 Gypsum Sheathing, and 07 84 43 Joint Firestopping. Put each one on the sheet so the bidder has to say yes or no.
- Walk the drawings for work no section names. Partition types, rated assemblies, head-of-wall details, and reflected ceiling plans each add lines.
- Write one priceable item per line. A bidder can price "Shaft wall assemblies at elevator, stair, and mechanical shafts" on its own. Nobody can compare two bids on "Drywall per plans".
- Give each gray-area line to one package. If firestopping belongs to another trade, leave it on the drywall sheet anyway. The Excluded mark then confirms the bidder agrees.
- Ask for breakout prices on a few lines. Pick the lines you expect to swap, cut, or plug, such as shaft wall or Level 5 finish.
- Add allowances, alternates, and unit prices. MasterFormat gives each its own Division 01 section: 01 21 00 Allowances, 01 22 00 Unit Prices, and 01 23 00 Alternates. Copy the amounts and descriptions from those sections.
- Fill in the header. List every drawing sheet, spec section, and addendum issued, with dates.
How to send the scope sheet with the invitation to bid
Attach the scope sheet to the invitation to bid, beside the drawings and specs, and ask for it back in Excel. A returned spreadsheet lets you copy the marks into your bid tab instead of retyping them from a PDF. Without a form to fill in, most bids arrive as a lump sum and a few paragraphs of scope, which is why subcontractor bids are incomplete.
Set the dates in the invitation. The AGC, ASA, and ASC guidelines suggest at least two weeks to prepare bids on a small project, and four to six weeks or more on a large one. They ask for the subcontractor's final price at least four hours before the general contractor's bid hour. They also ask the general contractor to set a cutoff time for subcontractor bids, announce it, and keep to it.
When an addendum changes the scope, send a revised scope sheet with new or reworded lines. Bidders then price the change on the same form. The guidelines also say subcontractors should not quote unapproved substitutions except as an alternate. The template gives them Alt 3 for that.
How to read and level returned scope sheets
Read each returned scope sheet against your own list, then put every bidder on the same lines before you compare prices. Base bids alone do not show what each bid leaves out.
- Check the header. Make sure each bidder acknowledged every addendum and signed.
- Read the status counts. The Excluded and Unclear counts show how much work each bid leaves open.
- Read the Exclusions sheet against the marks. A bidder may mark a line Included and then exclude part of it on the Exclusions sheet. Treat that line as Unclear until the bidder answers.
- Call about every Unclear line. Get each answer in writing.
- Plug the gaps. For each Excluded or still-Unclear line, add your price for the missing work to that bidder's total.
- Rank by leveled price. Compare totals only after every bidder covers the same scope.
The free bid leveling template takes the returned marks, adds plugs, and ranks the bidders. For the full method, read how to compare subcontractor bids. Keep each bidder's price to yourself. The guidelines say a general contractor should not reveal one bidder's price to another before it awards the subcontract.
A filled-in scope sheet example
The example below uses sample numbers from one drywall and framing bidder. The bidder marked all 31 lines, including one line it added. The table shows the lines with a price, a question, or an exclusion. The other 24 Included lines carry no price of their own.
| Scope line | Status | Price | Bidder's note |
|---|---|---|---|
| Base bid | $1,248,000 | ||
| Delegated design and stamped calculations for exterior framing | Excluded | Listed on the Exclusions sheet | |
| Glass-mat gypsum sheathing at exterior framed walls | Unclear | Is sheathing in the air barrier package? | |
| Shaft wall assemblies at elevator, stair, and mechanical shafts (break out) | Included | $86,400 | |
| Level 5 finish where the finish schedule shows it (break out) | Included | $23,750 | |
| Joint firestopping at the head of rated partitions | Excluded | By the firestopping subcontractor | |
| Allowance for added backing as directed by the GC: $15,000 | Included | $15,000 | |
| Temporary dust partitions at occupied areas (line the bidder added) | Included | $4,200 | |
| Prices entered on Included lines | $129,350 | ||
| Rest of the base bid (not broken out) | $1,118,650 | ||
| Lines marked Included / Excluded / Unclear | 28 / 2 / 1 | ||
| Alt 1: Level 5 finish at all corridor walls (add) | $31,500 | Not in the base bid | |
| Alt 3: Substitution the bidder proposes | -$6,400 | Different board maker, pending approval |
What the example scope sheet tells you
The example bid leaves three lines open before you can compare it. The two Excluded lines need plugs from your estimate or another bidder's price. The Unclear sheathing line needs a call, because the answer decides whether the drywall bid or the air barrier bid carries it.
The breakout also gives you swap prices. If the owner drops Level 5 finish, you know this bidder carried $23,750 for it. The base bid still covers $1,118,650 of work you cannot split further, so ask for more breakouts on the next package if you need them.
How Consight uses scope sheets
In Consight, each bid package has a scope sheet. Your scope items run down the left, and each bidder gets a column, as the help center's scope sheet guide shows. You can start the scope items by generating scope from your uploaded plans and specs. Or import a scope of work from Excel, or a takeoff exported from Bluebeam or OST. Lines from a BuildingConnected bid form also become scope lines.
When bids arrive, Level Bids goes through each processed bid and fills in the bidder columns against your scope items. Each bidder's cell on a line shows its coverage as Included, Not Included, or Needs Review. Request Bid Revision drafts an email to a bidder with a table of every scope item their bid excludes, leaves unclear, or does not address. Download saves the scope sheet as an Excel file.
The scope sheets reference covers each part of the scope sheet. To see the whole leveling workflow, visit bid leveling software.