Subcontractor Prequalification Form: Free Excel Template

Photo of Stewart ToubiaStewart ToubiaPreconstruction insights

A subcontractor prequalification form asks a sub for its safety record, finances, bonding capacity, insurance, licenses, references, and current workload. You review the answers before you invite the sub to bid. Download the free form as an Excel workbook or a printable PDF. The workbook works out the sub's recordable and DART rates and scores each sub on weights you set. It also sets the largest job you should award each sub.

To prequalify a subcontractor, you send the form well before bid day and check the key answers at their source. Then you score the sub and set a job size limit. You invite only the subs that pass, and you renew each approval at least once a year.

What questions belong on a subcontractor prequalification form?

A prequalification form should ask every question that tells you whether a sub can finish your job and pay its own people. The AGC's checklist on preventing subcontractor default groups these into financial review, insurance and bonding, references, company history, current projects, and claims and incident data, among others. The form follows the same groups:

Question on the form Why the GC asks Threshold or benchmark a source states
Legal name, former names, owners, parent company You need to know which entity signs the subcontract and whose balance sheet stands behind it. None; AGC says to understand "which entity you are contracting with"
Trades, self-performed work, and typical and largest contract size A sub that has never built a job this size is a risk, however good its price. None; set your own
Failed contracts, surety claims, lawsuits, liens, bankruptcy Past defaults and disputes are the plainest warning of the next one. None; set your own
Debarment or exclusion from public work Federal rules bar some subcontracts with excluded firms. FAR 9.405-2: on federal contracts, no subcontract over $45,000 with a debarred or suspended firm, with narrow exceptions
EMR for the last three years The EMR compares the sub's workers' compensation losses with the average employer in its class. Michigan Tech's form asks the GCs bidding to this public university for an EMR below 1.0 for the most recent year
Hours, recordable cases, DART cases, deaths, and OSHA citations Rates per hour worked let you compare a 20-person sub with a 200-person sub. BLS, 2024: construction averaged 2.2 recordable cases and 1.3 DART cases per 100 full-time workers
Revenue for three years, backlog, CPA statements, bank, credit AGC calls liquidity and consistent past performance "paramount considerations." None; NASBP says sureties ask for "fiscal year-end statements for at least the past three years"
Surety, single-job and aggregate bonding capacity, bonded backlog Bonding capacity caps the job size the sub can carry. The SFAA says GCs bond subs to use "the prequalification services of the surety." Michigan Tech may drop a bidder whose "bonding capacity will not cover the estimated cost of the project"
Insurance limits, carriers, and a certificate Your subcontract sets the limits; the form shows whether the sub carries them today. None; your contract sets them
Contractor and trade licenses You need proof the sub may legally do the trade's work where your job is. None; your state's licensing board sets them
References and current workload References show how the sub performed for other GCs. Workload shows whether it has crews free for you. None; AGC says to "Analyze volume for the last three years to understand capacity"

Two standard documents cover the same ground.

AIA A305-2020 is a sworn, notarized qualification statement with five optional exhibits: general information, financial and performance information, project-specific information, and two of past project experience. The AIA says subcontractors and suppliers can use it too.

ConsensusDocs 721 is the Subcontractor's Statement of Qualifications for a Specific Project. The ConsensusDocs catalog lists its schedules for key personnel, past projects, and current projects. Use one of them when your contract set already does. The free form here asks the same kinds of questions in a workbook that also scores the answers.

How do general contractors prequalify subcontractors?

General contractors prequalify subcontractors in six steps, from setting the bar to renewing approvals:

  1. Set your requirements first. Decide your EMR, insurance, and bonding requirements by job size before any sub applies. The AGC checklist asks for a fair, objective system that yields a short list of firms qualified to bid.
  2. Send the form before you build the bid list. Ask for it when a sub first wants to bid your work, and again before a job bigger than its last approval. Answers on file before bid day leave you free to level bids, not chase paperwork (see the construction bid day checklist).
  3. Check the key answers at their source. Do not score a number the sub typed without proof. The next section lists the documents to ask for.
  4. Score each sub on your weights. The Scoring sheet turns your 1-to-5 scores into one weighted score per sub.
  5. Set the largest job each sub can take. The Limits sheet works it out from bonding capacity, bonded backlog, and your own revenue cap.
  6. Invite only qualified subs, and renew. Record the score, the limit, and the date. Re-qualify each sub at least once a year and before any award that comes long after the approval.

How do you verify a subcontractor's answers?

You verify each key answer with a document that comes from someone other than the sub:

  • EMR: a letter from the insurer, or the rating worksheet. NCCI says its experience rating worksheets show the loss and payroll data behind the mod. A party other than the insurer needs "a written letter of authority from an insured" to get one. Michigan Tech asks for the EMR on a letter from the insurance carrier.
  • Safety rates: the OSHA Form 300A. Ask for the summary for each of the last three years. OSHA's recordkeeping rule makes employers keep these records for five years. A sub with 10 or fewer employees all last year may not keep them at all, under 29 CFR 1904.1. Look up the sub's inspections and citations in OSHA's establishment search, and match the address, since different companies can share a name.
  • Insurance: a certificate from the agent, plus the endorsements. A certificate alone proves little. The Nebraska Department of Insurance says certificates "do not and cannot amend, extend, or alter insurance coverage." Only the policy and its endorsements do. So when your subcontract names you as additional insured, ask for the endorsement itself.
  • Bonding: a call or letter from the surety agent about your job. NASBP warns that a general bondability letter shows only that the sub has a surety relationship. It "does not provide any kind of prequalification for a particular project," says NASBP's answers to 30 questions architects ask. For federal work, check the surety on the Treasury's Circular 570 list.
  • Exclusions: SAM.gov. FAR 9.404 says the System for Award Management lists debarred, suspended, and excluded firms.
  • References: phone calls. Call two or three GCs from the References sheet, a supplier, the bank, and the surety. AGC lists all four kinds of reference.

How do you check a subcontractor's safety numbers?

You check a sub's safety numbers by working out the rates yourself from its hours and cases.

OSHA's recordkeeping forms package gives the formulas. The total recordable incident rate (TRIR) is total recordable cases times 200,000, divided by hours worked by all employees. The DART rate uses only the cases with days away from work or with job transfer or restriction (columns H and I on the 300A). OSHA explains that 200,000 hours is what 100 employees work at 40 hours a week for 50 weeks.

The Safety sheet does this math for each year and for the three years together. Rates swing hard from year to year. At 210,000 hours a year, each recordable case adds 0.95 to the TRIR. So judge the three-year rate, and ask about any single bad year.

The EMR needs its own reading. NCCI's ABCs of Experience Rating says a mod below 1.00 is a credit and a mod above 1.00 is a debit. NCCI usually rates the latest three years of data available, and it never uses the current policy.

NCCI's plan does not apply in California, Delaware, Michigan, New Jersey, New York, or Pennsylvania. It also skips North Dakota, Ohio, Washington, and Wyoming, whose state funds run their own plans. California's WCIRB states its mod as a percentage, where less than 100% is better than average.

How do you score subcontractors and set a job limit?

You score each sub from 1 to 5 on each criterion, weight the criteria, and then cap the job size by bonding and revenue. First, set the weights on the Scoring sheet so they add up to 100%. Then score each sub.

The sheet multiplies each score by its weight and divides by the weights you scored. A blank score drops out, so a criterion that does not apply to a sub does not pull its score down.

Treat some answers as pass or fail before you score. A sub that is excluded in SAM.gov, has no license for your state, or cannot bond a bonded job fails, whatever its score. Write those must-pass items into your requirements in step 1.

The job limit comes from the Limits sheet. NASBP defines the two bonding limits. The single limit is the "maximum value of a single bond for any project." The aggregate limit is the most bonded work the sub can carry at once. The sheet subtracts bonded work on hand from the aggregate limit to find the room left. It then takes the lowest of three numbers:

  • the single-job bonding limit,
  • the aggregate bonding left, and
  • your own cap on one job as a share of the sub's annual revenue, if you set one.

No standard sets that revenue cap; choose it with your risk team, or leave it blank.

What does a filled-in prequalification scoring sheet look like?

The example below uses sample numbers for three drywall subs bidding a $3,000,000 package. The GC set these weights and gave each sub a score from 1 to 5.

Criterion Weight Bidder 1 Bidder 2 Bidder 3
Safety: EMR, recordable, and DART rates 25% 4 2 5
Financial strength 15% 3 5 4
Bonding 15% 4 5 3
Insurance limits 10% 5 5 5
Experience with this type and size 15% 4 5 3
References from general contractors 10% 4 4 5
Current workload and crews free 5% 3 4 5
Licenses and registrations 5% 5 5 5
Weighted score (1 to 5) 100% 3.95 4.10 4.25

Bidder 1's score works out as 0.25 × 4 + 0.15 × 3 + 0.15 × 4 + 0.10 × 5 + 0.15 × 4 + 0.10 × 4 + 0.05 × 3 + 0.05 × 5 = 3.95. The GC set its revenue cap at 25% of a sub's annual revenue. The Limits sheet then gave:

Limit Bidder 1 Bidder 2 Bidder 3
Annual revenue, most recent year $18,000,000 $9,000,000 $30,000,000
Bonding capacity, single job $5,000,000 $3,000,000 $8,000,000
Bonding capacity, aggregate $12,000,000 $6,000,000 $20,000,000
Bonded work on hand $8,500,000 $1,200,000 $9,000,000
Aggregate bonding left $3,500,000 $4,800,000 $11,000,000
Revenue cap at 25% $4,500,000 $2,250,000 $7,500,000
Largest job to award $3,500,000 $2,250,000 $7,500,000

Bidder 1's safety record behind its score of 4, from the Safety sheet:

Safety record 2025 2024 2023 3 years
EMR 0.82 0.88 0.95
Hours worked 210,000 195,000 176,000 581,000
Recordable cases 3 2 1 6
DART cases 2 1 1 4
TRIR 2.86 2.05 1.14 2.07
DART rate 1.90 1.03 1.14 1.38

What does the example scoring sheet tell you?

The example scoring sheet shows that the best score does not settle who may bid. Bidder 2 scores 4.10, second best, but its limit is $2,250,000. The package is $3,000,000, so Bidder 2 stays off this bid list. The cap comes from the GC's revenue rule, not from Bidder 2's bonding. A GC with no revenue cap would let Bidder 2 bid up to its $3,000,000 single-job limit.

Bidder 1 qualifies with $500,000 of room, so its surety should confirm it will bond this job. Bidder 1's three-year TRIR of 2.07 sits under the 2.2 BLS construction rate for 2024. Its latest year, at 2.86, does not, so ask what happened in 2025. Bidder 3 qualifies with the most room and the best score.

How often should you re-qualify a subcontractor?

Re-qualify each subcontractor at least once a year, and again before a large award. Michigan Tech, for example, makes its general contractors prequalify every year, and each approval expires on December 31. AGC's checklist says to update prequalification before award "if significant time has passed." It also says to request updated financials, including work in progress and backlog, as the work goes on.

Some events call for a new review mid-year. Look again at a new EMR or financial statement, a change in ownership or bonding, or a job bigger than the sub's last limit. AGC suggests you ask the sub to tell you when its executive team or ownership changes.

How does prequalification fit with bid leveling?

Prequalification decides who may bid. Bid leveling decides which qualified bid costs least for the full scope. On bid day, check each bid's qualifications against what the sub told you in prequalification. A bid can still exclude its bond cost or take exception to your insurance terms. The free bid leveling template has rows for EMR, insurance, bonding, and schedule under Qualifications.

Consight reads each bid and adds the exclusions it states to the scope sheet's Exclusions section, so an excluded bond or insurance cost shows next to the price. For how one package's award turned on more than price, see which subcontractor to award when the low bid isn't lowest.

Where Consight fits

Consight is the preconstruction workspace built around this kind of work—from understanding project documents and building scopes to collecting bids, leveling proposals, reviewing risk, and documenting the final award.